Kinoya WWTP is Suva's Waste Water Treatment Plant.
Despite a recent upgrade, it still runs mainly manually. WAF are in the process of upgrading the plant.
We installed the mechanical mechanism and electrical controls for a third and new Secondary Clarifier.
In 2014 we installed a new Trickling Filter and installed Plastic Media on all three of the filters. Upgraded 4 Re-Circ Pumps and installed and automated desludging actuators on the primary clarifiers.
In 2013 we completed a new Low Lift Pump Station, replaced the 1600amp main switchboard, Low Lift Station MCC, Control panel and equipment to allow full automation. A local Touch Screen allows setting of parameters and the system is all ready to be connected to the site SCADA